Assess the risk of a safety report

To assess the risk of a safety report, open the Risk assessment tab and click Rate initial risk. Select the cell of the risk matrix for the likelihood and the severity, and then click Save. Tailplane shows the risk index and the tolerability, for example "3B Tolerable".

Rate the risk of a safety report

  1. Go to Safety management > Safety reports.
  2. Click the reference number of the safety report.
  3. Click the Risk assessment tab.
  4. Click Rate initial risk. If the safety report has a rating, click Rate risk.
  5. In the risk matrix, click the cell for the likelihood and the severity.
  6. Make sure that the Result is correct.
  7. Optional: enter the Rationale.
  8. Click Save.

Rate the initial risk dialog with the risk matrix and a selected cell

The tab shows the current rating, the employee that rated it, the date and the rationale. The History list shows all the ratings.

Risk assessment tab with the current risk and the rating history

Risk matrix

The risk index is the likelihood number and the severity letter. For example, 4C is Occasional and Major.

Likelihood A Catastrophic B Hazardous C Major D Minor E Negligible
5 Frequent Intolerable Intolerable Intolerable Tolerable Tolerable
4 Occasional Intolerable Intolerable Tolerable Tolerable Tolerable
3 Remote Intolerable Tolerable Tolerable Tolerable Acceptable
2 Improbable Tolerable Tolerable Tolerable Acceptable Acceptable
1 Extremely improbable Tolerable Acceptable Acceptable Acceptable Acceptable

Things to know

  • The matrix is the example safety risk matrix of ICAO Doc 9859. You cannot change it.
  • A safety report has only an initial risk. Each new rating adds an entry to the history. The latest rating is the current risk.
  • When you click Rate risk, the dialog selects the cell of the latest rating.
  • The Risk column of the safety reports list shows the current risk.
  • Users with the View safety reports permission can see the tab. Users without the Manage safety reports permission see the text "Your safety manager will rate this report." when there is no rating.
  • The E5X export needs an initial risk rating.
  • Residual risk and risk acceptance apply to hazards, not to safety reports. Refer to Manage the hazard register and Accept residual risk.
Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.