Accept residual risk

When the residual risk of a hazard is Tolerable, a user with the Accept safety risk permission must accept it. Open the hazard, go to the Risk assessment tab, click Accept risk, enter the rationale, and then click Accept risk again.

Before you start

The hazard must have a residual risk rating. A user with the Manage hazard register permission rates it. Refer to Manage the hazard register.

Rate the residual risk

  1. Go to Safety management > Hazard register.
  2. Click the reference number of the hazard.
  3. Click the Risk assessment tab.
  4. Click Rate residual risk.
  5. In the risk matrix, click the cell for the likelihood and the severity with the new controls in place.
  6. Optional: enter the Rationale.
  7. Click Save.

Accept the residual risk

  1. Go to Safety management > Hazard register.
  2. Click the reference number of the hazard.
  3. Click the Risk assessment tab.
  4. In the Residual risk card, click Accept risk.
  5. In Rationale, state why the residual risk is as low as reasonably practicable.
  6. Click Accept risk.

The card shows Accepted, the name of the employee, the date and the rationale.

Risk assessment tab of a hazard with an accepted residual risk

Fields

  • Rationale: required. Why the residual risk is as low as reasonably practicable.

Things to know

  • Accept risk shows only when all these conditions are true:
    • The residual risk is Tolerable.
    • The hazard status is Open.
    • You have the Accept safety risk permission.
  • An Acceptable residual risk does not need an acceptance.
  • You cannot accept an Intolerable risk. Add corrective actions to reduce the risk, and then rate the residual risk again. Refer to Track corrective actions.
  • The acceptance applies to one residual rating. If a user rates the residual risk again, the new rating needs a new acceptance.
  • You can accept a rating only once.
  • To set a hazard to Mitigated, its current risk must be Acceptable, or Tolerable and accepted.
  • To open a hazard, the user must also have the View hazard register or Manage hazard register permission.
  • The tolerability of each cell of the risk matrix is in Assess the risk of a safety report.